Automatic capsule filling Machine maintenance and maintenance
10 Switch on: The operation of the point of the capsule hopper and material hopper loaded with sufficient qualified capsules and according to the production process requirements for the provision of good materials. Power switch to I "position, the total power LED light. Open the vacuum pump switch, press the vacuum pump button, the vacuum pump indicator light is on, the pump starts to work. Vacuum gauge pressure should be -0.06mpa. According to the feeding mode key feeding select key, manual mode indicator light. Press the manual feeding key, the feeding motor work, when the material level reaches the predetermined height, the feed motor automatically stops. Click on the click/Run key to switch its state to the point-and-move mode. Press the Start button, the main motor indicator light, the machine began to operate, at this time, observe the machine operation and the finished product (Frequency converter control keyboard on the frequency display is not zero machine operation, or the machine does not run). After all normal, loosen the button, the machine stops to turn. (Vacuum pump, feed motor, main motor, three motor can be started separately)
11 Boot
11.1 Press the point move/Run key, switch it to "run" state, while the indicator light is on, the machine is in automatic state.
12 11.2 Check the capsule appearance and weigh the capsule weight, whether meet the process requirements. 11.3 At any time to observe the operation of the machine, found that problems should be adjusted in time. 11.4 According to the need to adjust the speed of the machine, according to frequency converter control keyboard on the ∧ keys can increase the frequency, the motor speed rise, the output increases; Press ∨ key, will make the frequency drop, the output reduces. 12 Downtime 12.1 First press the Stop button, the host stopped working, and then pressed the vacuum pump button, the vacuum pump stopped working.
12.2 Closes the water section door, which closes the total power supply finally.
12.3 Finally according to "automatic capsule filling machine Clean regulations" to clean. Note: When the machine is in operation, the hands or objects are strictly prohibited from touching the operation parts.
13 Maintenance
14 Maintenance personnel must be familiar with the contents of this procedure, in the overhaul should be carried out in accordance with this procedure.
14.1 Maintenance category and interval Maintenance category general maintenance overhaul maintenance interval at any time of one year or need 15 maintenance content
15.1 General maintenance Check the linkage parts are loose, tighten each fastener, if there is overflow or gasket broken should be updated. Check the capsule after filling, if the capsule can not be tightly closed, should adjust the pressure of the top bar position, do not make the pressure plate clearance too large. Check the electrical wiring end is solid and reliable. 16 Overhaul
16.1 Carefully check the measurement plate, copper plate, module, push rod, Cam roller, chain, gearbox, found that the problem should be repaired or replaced in a timely manner.
16.2 Before the overhaul of the preparation work to cut off the power of the machine, and suspension of the "Prohibit start" warning signs. Remove extraneous utensils and sundries around the machine. Familiar with maintenance procedures, machine instructions and maintenance matters should be noted. 16.3 Inspection method completely clear the powder and capsule inside the hopper. Clean the dirt inside the machine. Visually inspect the parts of the machine for abnormalities. 16.4 The disassembly and disassembly method of the machine should follow the Top-down method.